Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the complianz-gdpr domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/bintcommtv/www/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the polylang domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/bintcommtv/www/wp-includes/functions.php on line 6114
Reprise des accès et du parking du site industriel Siegfried – B4 Design & Engineering

Reprise des accès et du parking du site industriel Siegfried

Saint Vulbas, France

|

2016

Infrastructures VRD

Projet

Afin d’améliorer la circulation interne du site et de faciliter les contrôles d’accès et donc sa sécurité, la société SIEGFRIED envisage de modifier les circulations sur le site et de les centraliser avant un contrôle de sureté.​


Périmètre de réflexion

7 ha


nos missions

Etudes préliminaires

Etudes de faisabilité technique et estimation des coûts de travaux pour la réorganisation des accès : ​

  • Création d’un nouvel accès unique intégrant un poste d’accueil et un contrôle d’accès​
  • Modification de l’implantation du parking VL personnel et visiteurs​
  • Création d’un emplacement de stockage de Poids lourds​

Concepteur

G.L.I Groupe EKIUM


Client

Société SIEGFRIED