Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the complianz-gdpr domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/bintcommtv/www/wp-includes/functions.php on line 6114
Construction of 13 buildings – B4 Design & Engineering

Construction of 13 buildings

Bourg-en-Bresse, France

|

2021

VRD Infrastructure

Project

Creation of 13 buildings with 2 to 3 floors, without basements, as well as parking lots, roadways, and green spaces.


Scope of Reflection

260 000 m²


our missions

AVPPreliminary Design

  • Study of the connections of the buildings to the existing and projected rainwater and wastewater networks
  • Leveling study of the building platforms
  • Road study including road geometry and suitable road structures
  • Cost estimation with a detailed price list outlining VRD interventions per building.

Designer


Client

URBAT